The schedule baseline is a component of what?

You work as a project manager for BlueWell Inc. There have been changes to the project scope in
your project. These changes will cause the project schedule to change as well, so you will need to
update the schedule and the schedule baseline. The schedule baseline is a component of what?

PrepAway - Latest Free Exam Questions & Answers

A.
Project calendar

B.
Project constraints

C.
Project objectives

D.
Project management plan

Explanation:
The schedule baseline is a required component of the project management plan. Project
management plan is a formal, agreed document that defines how the project is executed,
monitored and controlled. It may be summary or detailed and may be composed of one or more
subsidiary management plans and other planning documents. The objective of a project
management plan is to define the approach to be used by the project team to deliver the intended
project management scope of the project. The project manager creates the project management
plan with the inputs from the project team and key stakeholders. The plan should be agreed and
approved by at least the project team and its key stakeholders.
Answer option C is incorrect. The schedule baseline is not a project objective.
Answer option A is incorrect. The project calendar defines when the project will take place.
Answer option B is incorrect. Project constraints are restrictions imposed on the project, such as
time, cost, and scope.