Which of the following plans will you use to define how resources are brought onto the project team…?

You work as a project manager for BlueWell Inc. Which of the following plans will you use to
define how resources are brought onto the project team, how they are managed while on the
project team, and how they may be released from the project team?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Schedule Management Plan

B.
Project Staffing Management Plan

C.
Project Human Resources Management Plan

D.
Project Communications Management Plan

Explanation:
The project staffing management plan will define how resources are brought onto the project team,
how they are managed while on the project team, and how they may be released from the project
team. The staffing management plan is part of human resources plan. It is a subsidiary plan of the
overall project management plan and defines when project team members will be brought onto
and released from the project. It describes when and how human resource requirements will be
met. Depending upon the needs of the project, it can be formal or informal, highly detailed or

broadly framed. The staffing management plan may include the following items: Staff acquisition,
resource calendars, staff release plan, training needs, recognition and rewards, compliance, and
safety.
Answer option D is incorrect. The communications management plan defines project
communication requirements and expectations.
Answer option C is incorrect. This is not a valid project management plan.
Answer option A is incorrect. The project schedule management will define when resources are
needed and scheduled. But it will not define how resources are allowed to be released from the
project.