PrepAway - Latest Free Exam Questions & Answers

Where can you find a list of the project milestones to anticipate management’s request?

You work as a project manager for BlueWell Inc. Management has asked you to communicate
with them whenever your project is about to reach a milestone so that they can review your project
performance to date. Where can you find a list of the project milestones to anticipate
management’s request?

PrepAway - Latest Free Exam Questions & Answers

A.
Scope baseline

B.
Milestone list

C.
Project charter

D.
Project Schedule Management Plan

Explanation:
The milestone list is the best answer. A milestone list provides a sequence of indicators about
project progress to date and achievements or goals, which are to be achieved. The milestone list
is used in project management as an indication of progress through the achievement of a major
project accomplishment. It is a project document that is not part of the project management plan.
The list contains all the project milestones along with information indicating whether they are
mandatory to achieve or not.
Answer option A is incorrect. The scope baseline is a collection of the project scope, the WBS,
and the WBS dictionary.
Answer option D is incorrect. The project schedule management plan is not the best answer, as
the milestone list is the most direct result.