Choose and reorder the steps that she should follow while creating the schedule for the project.
Michelle works as a scheduler in Array Inc. She has to create a schedule for a project assigned to
her. Choose and reorder the steps that she should follow while creating the schedule for the
project. Select an item from the right pane.
Explanation/Reference:
Schedule development is the process of analyzing activity sequences, durations, resource
requirements, and schedule constraints to create the project schedule. Inserting the activities,
durations, and resources into the scheduling tool generates a schedule with planned dates for
completing the project activities. The goal of the schedule development is to form the processes
such that the stakeholders can use it in the creation of the project. Schedule development consists
of two main sections:
1. Input and Data: The starting point for any schedule is the input of information developed during
the planning process.
Define schedule scope
Breakdown structure relationships
Schedule specification
Feedback from stakeholders
Cost estimate model
2. Creating Schedule: This process provides basic knowledge in an outline structure for a study of
the means, methods, and tools necessary for the project schedule development process.
Types of schedules
Activities
Durations Relationships Constraints and calendars Cost and resource loading Schedule quality
analysis and compliance review Schedule basis documentation
Choose and reorder the essential steps required in developing the scheduling framework.
Choose and reorder the essential steps required in developing the scheduling framework. Select
an item from the right pane.
Explanation/Reference:
The essential steps required in developing the scheduling framework are as follows: 1.Determine
how the schedule model will be developed.
2.Understand the full scope of the project.
3.Identify the project and schedule.
4.Establish project calendars and work periods.
5.Establish the optimum project update cycle.
6.Design an effective activity coding structure.
7.Determine resource planning requirements.
Choose and reorder the essential steps required in developing the baseline schedule. Select an
Choose and reorder the essential steps required in developing the baseline schedule. Select an
item from the right pane.
Explanation/Reference:
The essential steps required in developing the baseline schedule are as follows:
1.Define Milestones.
2.Design the Project’s Activities.
3.Design the Project’s Logic.
4.Determine the Duration for Each Activity.
5.Analyze the Schedule Output.
6.Approve the Schedule.
7.Baseline the Schedule.
8.Maintain the Schedule.
what process may happen next?
Once the project’s WBS has been created what process may happen next?
Which of the following scheduling techniques identifies the successor activities and the predecessor activitie
Which of the following scheduling techniques identifies the successor activities and the
predecessor activities to assist the project manager in sequencing the project work?
What communication technique do you normally use to distribute reports?
You are the project manager of the NHGQ project for your company. You must create and
distribute performance reports every week to your key project stakeholders. What communication
technique do you normally use to distribute reports?
Which approach could you use to shorten the duration of the project?
Your project team is executing the project plan and things are going well. Your team has reached
its first milestone and is now in the second phase of the project. The project stakeholders have
requested that you find a method to reduce the duration of the project. They will reward you and
your project team with a 25 percent bonus of the project costs if you can finish the project thirty
days earlier than what was already planned. The stakeholders, however, will not approve any
additional labor costs as part of the agreement. Which approach could you use to shorten the
duration of the project?
Which one of the following is not an output of the Define Activities process?
The Define Activities process is the first process in the project time management knowledge are a.
The Define Activities process creates just three outputs as a result of decomposition, rolling wave
planning, templates, and expert judgment. Which one of the following is not an output of the
Define Activities process?
how long can you now delay Activity H?
what a milestone is?
You are the project manager of the GHT Project. Ben, one of your project team members, does
not understand the idea of a milestone. Which of the following best describes what a milestone is?