Which of the following scheduling techniques identifies the successor activities and the predecessor activitie

Which of the following scheduling techniques identifies the successor activities and the
predecessor activities to assist the project manager in sequencing the project work?

PrepAway - Latest Free Exam Questions & Answers

A.
Precedence Diagramming Method

B.
Schedule network template

C.
Dependency determination

D.
Activity on the Node

Explanation:
The Precedence Diagramming Method uses both predecessors and successors as nodes in the
project network diagram. The PDM approach is the most common network diagram approach
used.
Answer option C is incorrect. Dependency determination identifies the order of the project work.
Answer option B is incorrect. The schedule network template is a tool that uses a previous project
network diagram as a base for the current project network diagram.
Answer option D is incorrect. Activity on the node places activities on circles within a network
diagram. It is an example of the precedence diagramming method.