Which calendar will communicate to the project stakeholders, when the project work will take place within the

You are the project manager for your organization. Management has asked you to document the
holidays, weekends, and other corporate working hours, which will supersede the project timings
for your schedule. Which calendar will communicate to the project stakeholders, when the project
work will take place within the organization?

PrepAway - Latest Free Exam Questions & Answers

A.
Project calendar

B.
Resource calendar

C.
Organizational calendar

D.
Company calendar

Explanation:
The project calendar defines the working hours for the project, including any days that project work
will not happen due to the organizational calendar.
Answer option D is incorrect. The company calendar is not the correct choice for this question.
Answer option C is incorrect. The organizational calendar is not the correct choice for this
question.
Answer option B is incorrect. The resource calendar defines whether resources the project needs
will be available. The resources include people, facilities, equipment, and other things that project