What process will examine the change to this project process and implement it in the project?

You are the project manager of the NNN Project. Stakeholders in the two-year project have
requested to send status reports to them via email every week. You have agreed and are sending
the reports on each Thursday. After six months of the project, the stakeholders are pleased with
the project progress and they would like you to reduce the status reports to every two weeks.
What process will examine the change to this project process and implement it in the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Project change control process

B.
Perform integrated change control process

C.
Configuration management

D.
Communications management

Explanation:
Although this appears to be a simple change the project manager must still follow the rules of the
project’s change control system. Perform Integrated Change Control is the process of reviewing all
change requests, approving changes, and controlling changes to the deliverables and
organizational process assets in a project. Perform Integrated Change Control has to do with
influencing the things that cause change, determining that the change is required or has
happened, and managing the change.
Answer option D is incorrect. Communications management is the execution of the
communications management plan.
Answer option A is incorrect. The project change control process not valid as it’s the parent of the
integrated change control process, which is more accurate for this question.
Answer option C is incorrect. Configuration management is the documentation and control of the
product’s features and functions.