Which one of the following is NOT an input to the control schedule process?

You are the project manager for your organization. You are working through the control schedule
process. According to the PMBOK, there are four inputs to this process. Which one of the
following is NOT an input to the control schedule process?

PrepAway - Latest Free Exam Questions & Answers

A.
Schedule data

B.
Work performance information

C.
Project management plan

D.
Project schedule

Explanation:
Schedule data is not an input to the control schedule process. Organizational process assets are
the final input to the control schedule process. The inputs of schedule control process are as
follows: Project Management Plan Project Schedule Work Performance Integration Organizational
Process Assets
Answer option C is incorrect. The project management plan is an input to the control schedule
process.
Answer option D is incorrect. The project schedule is an input to the control schedule process.
Answer option B is incorrect. Work performance information is an input to the control schedule
process.

One Comment on “Which one of the following is NOT an input to the control schedule process?

  1. xxx says:

    correct answer is B

    Inputs are:

    .1 Project management plan
    .2 Project schedule
    .3 Work performance data
    .4 Project calendars
    .5 Schedule data
    .6 Organizational process assets

    Outputs:

    .1 Work performance information
    .2 Schedule forecasts
    .3 Change requests
    .4 Project management plan updates
    .5 Project documents updates
    .6 Organizational process assets updates