What project management process are you working with when you create a new target schedule?

You work as a project manager for BlueWell Inc. Some of the activities in your project are not
being completed on time. You review these activities with your project team discovered that the
time estimates for the project are much more aggressive than what they are actually experiencing
in the completion of the activities. You decide on to create a new schedule for the project. What
project management process are you working with when you create a new target schedule?

PrepAway - Latest Free Exam Questions & Answers

A.
Estimate activity durations

B.
Estimate activity resources

C.
Control schedule

D.
Develop schedule

Explanation:
In severe cases, new schedule duration estimates with new forecasted start and finish dates are
needed. In these instances, it is an example of using the control schedule process. Control
schedule process is a method of monitoring the status of the project to update project progress
and deal with the changes to the schedule baseline. It is concerned with: Determining the current
status of the project Influencing the factors that create schedule changes Determining that the
project schedule has changed Managing the actual changes as they occur Control schedule is a
component of the Perform Integration Change Control process.
Answer option B is incorrect. The activity resources would only address the addition or
replacement of resources needed to complete the project work.
Answer option A is incorrect. This is a tempting choice, but according to the PMBOK, new
schedules are part of the control schedule process.
Answer option D is incorrect. Develop schedule is not the best choice for this question. It is a
process of analyzing activity sequences, durations, resource requirements, and schedule
constraints to create the project schedule.