What is the main output of the identify stakeholders process?

Sam is the project manager of the NQQ project. He and the project team have completed the
stakeholder identification process for his project. What is the main output of the identify
stakeholders process?

PrepAway - Latest Free Exam Questions & Answers

A.
Communications management plan

B.
Stakeholder register

C.
Requirements

D.
Stakeholder management strategy

Explanation:
According to the PMBOK, the main output of the identify stakeholders process is the stakeholder
register. The stakeholder register is a project management document that contains a list of the
stakeholders associated with the project. It assesses how they are involved in the project and
identifies what role they play in the organization. The information in this document can be very
perceptive and is meant for limited exchange only. It also contains relevant information about the
stakeholders, such as their requirements, expectations, and influence on the project.
Answer option A is incorrect. The communications management plan is an output of
communications planning.
Answer option D is incorrect. The stakeholder management strategy is an output of stakeholder
identification, but it is not the main output.
Answer option C is incorrect. Requirements are not an output of the stakeholder identification
process.