PrepAway - Latest Free Exam Questions & Answers

Which of the following is NOT an output of the control schedule process?

Which of the following is NOT an output of the control schedule process?

PrepAway - Latest Free Exam Questions & Answers

A.
Organizational process assets

B.
Change requests

C.
Project termination request

D.
Project document updates

Explanation:
The project termination request is not an output of the control schedule. Early termination of a
project is a closing process and usually does not stem from the project manager. The outputs of

the control schedule process are as follows: Work Performance Measurements: The work
packages and control accounts are documented and communicated to the stakeholders.
Organizational Process Assets Updates: The assets that are updated are: corrective actions
chosen and the reasons, causes of variance, and other types of lessons learned from project
schedule control. Change Requests: It is processed for reviews and disposition through the
Perform Integrated Change Control process. Project Management Plan Updates: The elements
that need to be updated are: schedule baseline, schedule management plan, cost baseline.
Project Document Updates: The elements that need to be updated in project document updates
are: schedule data and project schedule.


Leave a Reply