PrepAway - Latest Free Exam Questions & Answers

which path is the critical path for this project?

Joseph works as the project manager of the NHQ Project. He has created the project network
diagram as shown in the figure:

Based on the network diagram, find out which path is the critical path for this project?

PrepAway - Latest Free Exam Questions & Answers

A.
ABEHJ

B.
ABDIJ

C.
ABDHJ

D.
ACFIJ

Explanation:
The critical path is the path with the longest duration to complete the project. It has no float and
shows the earliest completion date and the latest completion date for the project. In this example,
path ACFIJ takes 27 days and is the critical path.
ACFIJ= A(4)+C(8)+F(4)+I(7)+J(4)= 27
A critical path is the sequence of project activities, which add up to the longest overall duration.
This determines the shortest time possible to complete the project. Any delay of an activity on the
critical path directly impacts the planned project completion date (i.e. there is no float on the critical
path). A project can have several, parallel, near critical paths. An additional parallel path through
the network with the total durations shorter than the critical path is called a sub-critical or non-critical path. These results allow managers to prioritize activities for the effective management of
project completion, and to shorten the planned critical path of a project by pruning critical path
activities, by “fast tracking” (i.e., performing more activities in parallel), and/or by “crashing the
critical path” (i.e., shortening the durations of critical path activities by adding resources).
Answer option A is incorrect. ABEHJ takes only 22 days to complete.
ABEHJ= A(4)+B(5)+E(2)+H(7)+J(4)= 22
Answer option C is incorrect. ABDHJ takes 21 days to complete.
ABDHJ= A(4)+B(5)+D(1)+H(7)+J(4)= 21
Answer option B is incorrect. ABDIJ takes 21 days to complete.
ABDIJ= A(4)+B(5)+D(1)+I(7)+J(4)= 21


Leave a Reply