What component of the change management system is responsible for evaluating, testing, and documenting changes

What component of the change management system is responsible for evaluating, testing, and
documenting changes created to the project scope?

PrepAway - Latest Free Exam Questions & Answers

A.
Scope Verification

B.
Configuration Management System

C.
Project Management Information System

D.
Integrated Change Control

Explanation:
The change management system is comprised of several components that guide the change
request through the process. When a change request is made that will affect the project scope.
The Configuration Management System evaluates the change request and documents the
features and functions of the change on the project scope. What is Configuration Management
System? Configuration Management System is a subsystem of the overall project management
system. It is a collection of formal documented procedures used to identify and document the
functional and physical characteristics of a product, result, service, or component of the project. It
also controls any changes to such characteristics, and records and reports each change and its
implementation status. It includes the documentation, tracking systems, and defined approval
levels necessary for authorizing and controlling changes. Audits are performed as part of
configuration management to determine if the requirements have been met.
Answer option D is incorrect. Integrated Change Control, part of the change control system, does
not document changes to the features and functions of the project scope. It evaluates the
change’s impact on eight knowledge areas: scope, time, cost, quality, human resources,
communication, risk, and procurement. What is Perform Integrated Change Control? Perform
Integrated Change Control is the process of reviewing all change requests, approving changes,
and controlling changes to the deliverables and organizational process assets in a project.
Perform Integrated Change Control has to do with influencing the things that cause change,
determining that the change is required or has happened, and managing the change.
Answer option A is incorrect. Verify scope is a process of formalizing acceptance of the completed
project deliverables. It is an inspection- driven process the stakeholders will complete to inspect
the project scope deliverables. It is typically performed at the end of the phase and at the end of
the project.
Answer option C is incorrect. The Project Management Information System (PMIS) is an
information system consisting of the tools and techniques used to gather, integrate, and
disseminate the outputs of project management processes. It is used to support all aspects of the
project from initiating through closing, and can include both manual and automated systems. It is
the parent of the change control process. It is a system that includes all of the change control
processes for scope, time, cost, and procurement. Configuration management is part of the PMIS.