Choose and reorder the essential steps required in developing the baseline schedule. Select an
item from the right pane.
Answer: See the explanation.
Explanation/Reference:
The essential steps required in developing the baseline schedule are as follows:
1.Define Milestones.
2.Design the Project’s Activities.
3.Design the Project’s Logic.
4.Determine the Duration for Each Activity.
5.Analyze the Schedule Output.
6.Approve the Schedule.
7.Baseline the Schedule.
8.Maintain the Schedule.