PrepAway - Latest Free Exam Questions & Answers

Choose and reorder the essential steps required in developing the baseline schedule. Select an

Choose and reorder the essential steps required in developing the baseline schedule. Select an
item from the right pane.

PrepAway - Latest Free Exam Questions & Answers

Answer: See the explanation.

Explanation/Reference:

The essential steps required in developing the baseline schedule are as follows:
1.Define Milestones.
2.Design the Project’s Activities.
3.Design the Project’s Logic.
4.Determine the Duration for Each Activity.
5.Analyze the Schedule Output.
6.Approve the Schedule.
7.Baseline the Schedule.
8.Maintain the Schedule.


Leave a Reply