Which of the following are the inputs to the Develop Project Charter process?

Which of the following are the inputs to the Develop Project Charter process? Each correct answer
represents a complete solution. Choose all that apply.

PrepAway - Latest Free Exam Questions & Answers

A.
Procurement document

B.
Contract

C.
Business case

D.
Project statement of work

Explanation:
The Develop Project Charter process documents the formal authorization of a project or a phase.
It also documents initial requirements that satisfy the stakeholder’s needs and expectations. It is
used to validate the decisions made during the previous iteration of the Develop Project Charter
process. The various inputs of this process are as follows: Project statement of work
Business case
Contract
Enterprise environmental factors
Organizational process assets
The output of the Develop project Charter process is as follows:
Project charter
Answer option A is incorrect. Procurement document is the input of the Identify Stakeholders

process.