Which of the following are the outputs to the Determine Budget process?

Which of the following are the outputs to the Determine Budget process? Each correct answer
represents a complete solution. Choose all that apply.

PrepAway - Latest Free Exam Questions & Answers

A.
Project document updates

B.
Scope baseline

C.
Cost performance baseline

D.
Project funding requirements

Explanation:
The outputs to the determine budget process are as follows: Cost performance baseline: The cost
performance baseline is an authorized time-phased budget at completion. Project funding
requirements: The project funding requirements are determined from total funding requirements
and periodic funding requirements. Project document updates: The project document updates
consists of risk register, cost estimates and project schedule.
Answer option B is incorrect. Scope baseline is an input to the determine budget process.