Which one of the following is NOT an input to the Develop Schedule process?

You are the project manager for your organization. You and the project team are developing the
project schedule for your current project. In addition to the enterprise environment factors and the
organizational process assets, you will need seven other inputs to this process. Which one of the
following is NOT an input to the Develop Schedule process?

PrepAway - Latest Free Exam Questions & Answers

A.
Resource calendars

B.
Schedule data

C.
Activity list

D.
Project scope statement

Explanation:
Schedule data is an output of the Develop Schedule process. The nine inputs to the Develop
Schedule process are: activity list, activity attributes, project schedule network diagrams, activity
resource requirements, resource calendars, activity duration estimates, project scope statement,
enterprise environmental factors, and organizational process assets.
Answer options C, A, and D are incorrect. These are the inputs to the Develop Schedule process.