You are the project manager of the NHQ Project. Management has told you that resource leveling
will be enforced on your project, but they still want you to complete the project by July 2. With the
current resources you have and the resource leveling imposed, you would not be able to finish by
the constraint. What document should you update to address this situation?

PrepAway - Latest Free Exam Questions & Answers

A.
Project activity resource requirements

B.
Project schedule management plan

C.
Project scope

D.
Project charter

Explanation:
The activity resource requirements will need to be addressed because the imposed constraint will
cause a need for more resource to complete the activities by July 2. What is resource leveling
heuristics? Resource leveling heuristics is a prioritization method that allocates inadequate
resources to critical path activities first. It is a schedule network analysis technique useful to a
schedule that has already been analyzed by the critical path method. It is used when shared or
critical essential resources are only available at certain times, in limited quantities, or to keep
resource usage at a constant level. It is a technique that resolves resource conflicts by delaying
tasks within their slack allowances. Resource leveling is the process in which project teams come
across problems when developing their project schedules. If a company has multiple projects
running simultaneously that require the same resources, then problems can arise. It can often
cause the critical path method to change.
Answer option C is incorrect. The project scope does not need to be addressed as there has not
been a request to reduce or increase the project scope.

Answer option B is incorrect. The project charter will not change. In fact, the charter will rarely, if
ever, change once has been approved and signed.
Answer option D is incorrect. The schedule management plan would not be the biggest concern in
this instance. The plan defines how the schedule will be created, executed, monitored and
controlled.