Which of the following is an output of the control schedule process?

You work as the project manager for BlueWell Inc. Mark, a project team member, has some
doubts related to the outputs of the control schedule process. Which of the following is an output
of the control schedule process?

PrepAway - Latest Free Exam Questions & Answers

A.
Project schedule

B.
Lessons learned

C.
Change request

D.
Activity resource requirement

Explanation:
Only change request is a valid answer. The five outputs of the control schedule process are work
performance measurements, organizational process assets updates, change requests, the project
management plan updates, and project document updates. Change requests are requests to
expand or reduce the project scope, modify policies, processes, plans, or procedures, modify
costs or budgets or revise schedules. These requests for a change can be direct or indirect,
externally or internally initiated, and legally or contractually imposed or optional. A Project
Manager needs to ensure that only formally documented requested changes are processed and
only approved change requests are implemented.
Answer option D is incorrect. Activity resource requirement is not an output of the control schedule
process.
Answer option A is incorrect. The project schedule is not an output of the control schedule
process.
Answer option B is incorrect. Lessons learned is not an output of the control schedule process.