what project execution technique?

You are the project manager of the NHT Project. This project has 12,345 office doors to install
throughout a campus. Each of the doors costs the project $456 and requires special hardware to
electronically lock and open the doors. You’ve gathered the project team before they begin the
installation for a hands-on training. As a group you and the project team install 50 doors following
a checklist of instructions so that every door will be installed exactly the same throughout the
campus and with minimal waste. This is an example of what project execution technique?

PrepAway - Latest Free Exam Questions & Answers

A.
Preventive action

B.
Defect repair validation

C.
Implemented corrective action

D.
Quality control

Explanation:
This is an example of a preventive action as you’re working with the team before they install the
doors to train them on the installation. The checklist is a quality control tool but the question was
asking for a project execution activity. Preventive and corrective actions are part of project
execution.
Answer option D is incorrect. Quality control is a controlling and monitoring process, not an
executing process.
Answer option B is incorrect. The defect repair validation comes after the project team has
corrected an error – something that has not occurred in this instance.
Answer option C is incorrect. Corrective action is a response to something that needs to be
corrected in the project.