Which type of scheduling would be required in such a scenario?

You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise
building site. Your prime concern is to ensure that cranes are used effectively for moving
materials. You also have to ensure that delivery trucks do not have to wait in a queue and that
workers on the upper floors are able to get their deliveries on time. Which type of scheduling
would be required in such a scenario?

PrepAway - Latest Free Exam Questions & Answers

A.
Critical path scheduling

B.
Time-oriented scheduling

C.
Resource-oriented scheduling

D.
Network scheduling

Explanation:
Resource-oriented scheduling focuses on using and scheduling particular resources in an effective
manner. This type of scheduling should be used whenever there are limited resources available
for a project and the struggle for these resources between the project activities is intense. As a
result, delays are likely to arise in such cases, as actions must wait until general resources
become available. Resource-oriented scheduling is also suitable in cases where unique resources
are to be used, such as when there is only one excavator available in an excavation operation.
Answer option B is incorrect. Time-oriented scheduling is a time-scheduling method that focuses
on determining the finishing time of a project. It also specifies the crucial precedence relationships
among the activities involved in the project. In time-oriented scheduling, the appropriate time is
allocated for the whole project through the successive stages of the project life cycle.
Answer option A is incorrect. Critical path scheduling is a technique that calculates the minimum
completion time for a project along with the possible start and finish times for the project activities.
Answer option D is incorrect. Network scheduling provides a basis for obtaining facts for decision
making.