PrepAway - Latest Free Exam Questions & Answers

which of the following Knowledge Areas?

The Closing Process Group includes which of the following Knowledge Areas?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Risk Management and Project Procurement Management

B.
Project Integration Management and Project Procurement Management

C.
Project Risk Management and Project Integration Management

D.
Project Integration Management and Project Quality Management

7 Comments on “which of the following Knowledge Areas?

  1. vijaydugam says:

    Passed in 6th Edition exam. More and more new question.

    Dont check PMP 5th edition exam question . In 6th Edition new question was introduced. Very Logical question. From above dumps only 3 to 5 question was in exam




    5



    0

Leave a Reply