PrepAway - Latest Free Exam Questions & Answers

When would resource leveling be applied to a schedule model?

When would resource leveling be applied to a schedule model?

PrepAway - Latest Free Exam Questions & Answers

A.
Before constraints have been identified

B.
Before it has been analyzed by the critical path method

C.
After it has been analyzed by the critical path method

D.
After critical activities have been removed from the critical path


Leave a Reply