What is the MOST appropriate approach to managing this …

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the
product delivery. What is the MOST appropriate approach to managing this situation?

PrepAway - Latest Free Exam Questions & Answers

A.
Utilize the change control process.

B.
Crash the schedule to fix the defect.

C.
Leave the defect in and work around it.

D.
Fast-track the remaining development.