What is one of the objectives of Project Risk Management?

What is one of the objectives of Project Risk Management?

PrepAway - Latest Free Exam Questions & Answers

A.
Decrease the probability and impact of an event on project objectives.

B.
Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.
Increase the probability and impact of positive events.

D.
Removal of project risk.