When can pre-assignment of project team members occur?

When can pre-assignment of project team members occur?

PrepAway - Latest Free Exam Questions & Answers

A.
When the project uses capital expenditures

B.
When the required staff can be acquired from outside sources

C.
When the project would be ignored due to travel expenses

D.
When the project is the result of specific people being promised as part of a competitive proposal