PrepAway - Latest Free Exam Questions & Answers

The three types of estimates that PERT uses to define a…

The three types of estimates that PERT uses to define an approximate range for an activity’s cost are:

PrepAway - Latest Free Exam Questions & Answers

A.
Parametric, most likely, and analogous.

B.
Least likely, analogous, and realistic.

C.
Parametric, optimistic, and pessimistic.

D.
Most likely, optimistic, and pessimistic.


Leave a Reply