Which items are components of a project management plan?

Which items are components of a project management plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Change management plan, process improvement plan, and scope management plan

B.
Agreements, procurement management plan, and work performance information

C.
Schedule management plan, project schedule, and resource calendars

D.
Scope baseline, project statement of work, and requirements traceability matrix