What should you do to ensure the plan is effective and …

You are assigned to implement the project control plan. What should you do to ensure the plan is effective and
current?

PrepAway - Latest Free Exam Questions & Answers

A.
Perform periodic project performance reviews.

B.
Identify quality project standards.

C.
Follow ISO 9000 quality standards.

D.
Complete the quality control checklist.