Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting
changes to the project and for recording and communicating decisions?

PrepAway - Latest Free Exam Questions & Answers

A.
Project team

B.
Focus group

C.
Change control board

D.
Project stakeholders