Inputs to the Plan Schedule Management process include:

Inputs to the Plan Schedule Management process include:

PrepAway - Latest Free Exam Questions & Answers

A.
Organizational process assets and the project charter,

B.
Enterprise environmental factors and schedule tools.

C.
Time tables and Pareto diagrams.

D.
Activity attributes and resource calendars.