Organizations perceive risks as:
A.
events that will inevitably impact project and organizational objectives.
B.
the effect of uncertainty on their project and organizational objectives.
C.
events which could have a negative impact on project and organizational objectives.
D.
the negative impact of undesired events on their project and organizational objectives.