In a construction project schedule, what is the logical relationship between the delivery of the concrete materials
and the pouring of concrete?

PrepAway - Latest Free Exam Questions & Answers

A.
Start-to-start (SS)

B.
Start-to-finish (SF)

C.
Rnish-to-finish (FF)

D.
Finish-to-start (FS)