Which schedule method allows the project team to place …

Which schedule method allows the project team to place buffers on the project schedule path to account for
limited resources and project uncertainties?

PrepAway - Latest Free Exam Questions & Answers

A.
Critical path method

B.
Critical chain method

C.
Resource leveling

D.
Schedule network analysis