When a control chart is used to monitor performance of a process, which of the following will be set by the
project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken
to prevent exceeding the specification limits?

PrepAway - Latest Free Exam Questions & Answers

A.
Upper and lower control limits

B.
Upper and lower specification limits

C.
Process mean

D.
Data points