Which of the following is a project constraint?

Which of the following is a project constraint?

PrepAway - Latest Free Exam Questions & Answers

A.
Twenty-five percent staff turnover is expected.

B.
The technology to be used is cutting-edge.

C.
Project leadership may change due to volatile political environment.

D.
The product is needed in 250 days.