Which of the following is developed from the project sc…

Which of the following is developed from the project scope baseline and defines only that portion of the project
scope that is to be included within a related contract?

PrepAway - Latest Free Exam Questions & Answers

A.
Product scope description

B.
Procurement statement of work

C.
Project schedule

D.
Work breakdown structure (WBS)