PrepAway - Latest Free Exam Questions & Answers

You have created a project network diagram as shown in the figure: Based on this diagram, find out the earli

You work as the project manager for Blue Well Inc. You are working with your project team to
schedule the days the project work will take place. You have created a project network diagram as
shown in the figure:

Based on this diagram, find out the earliest day on which Activity G can be started.

PrepAway - Latest Free Exam Questions & Answers

A.
Day 13

B.
Day 7

C.
Day 22

D.
Day 17

Explanation:
The earliest Activity G can start is Day 17. This is because activities A, D, C, and F must all be
completed before Activity G can start.
Answer option A is incorrect. Day 13 does not account for Activity F since Activity F is also a
predecessor to Activity G.
Answer option C is incorrect. Day 22 is the earliest Activity G can finish.
Answer option B is incorrect. Day 7 is not a valid answer.


Leave a Reply