Who should Nancy deliver this final project report to if she is participating in a projectized structure?

Nancy is the project manager of the JJJ Project. This project has recently been approved by the
project customer as complete so Nancy must now finalize the administrative closure. Nancy needs
to create the final project report to report the successes and failures in the project. Who should
Nancy deliver this final project report to if she is participating in a projectized structure?

PrepAway - Latest Free Exam Questions & Answers

A.
Functional Management

B.
Project sponsor

C.
Whomever the communications management plan directs her to

D.
Project customer

Explanation:
The communications management plan will define who will receive what information.
Answer option B is incorrect. The project sponsor may be a recipient but the project
communications management plan is the best selection.
Answer option A is incorrect. Functional management is not the best choice in a projectized
structure.
Answer option D is incorrect. The project customer may receive a copy of the report, but the
project communications management plan should direct the communications.