You are the project manager of the MQQ project. Unfortunately, this project is not performing well
and you must do something to address the problems in your project. Based on your planning for
monitoring and controlling project performance, you know that there are three outputs of
performance reporting. Which one of the following is the only output that is most appropriate for
this poorly performing project?

A.
Organizational process assets update
B.
Performance reports
C.
Performance re-baselining
D.
Change requests
Explanation:
Change requests are an output of performance report, and allow the project manager to address
corrective actions and preventive actions to help the project get back in alignment with
performance baselines.
Answer option B is incorrect. While performance reports are an output of the performance
reporting, these reports do not specifically address the problems in the project.
Answer option A is incorrect. Updating the organizational process assets is an important activity,
but it does not address the poor performance directly.
Answer option C is incorrect. Performance re-baselining is not an output of performance reporting
so this choice is not valid.