There are seven inputs to the estimate activity durations process. Which one of the following is
NOT an input to this process?

A.
Scope baseline
B.
Activity attributes
C.
Activity list
D.
Activity resource requirements
Explanation:
The scope baseline is not an input to the estimate activity durations process. The project’s scope
statement is an input, but according to the PMBOK, the scope baseline is not. The seven inputs to
this process are: activity list, activity attributes, activity resource requirements, resource calendars,
project scope statement, enterprise environmental factors, and organizational process assets.
Answer options C, B, and D are incorrect. These all are an input to the estimate activity durations
process.