Harry works as a project manager for BlueWell Inc. He is determining the budget of the project.
According to the PMBOK, there are seven inputs to this process. Which one of the following is
NOT an input to the determine budget process?

A.
Contract
B.
Reserve analysis
C.
Scope baseline
D.
Project schedule
Explanation:
Reserve analysis is not an input to the determine budget process. It is a technique used for
determining the budget. The inputs to the determine budget process are as follows: Activity cost
estimates Basis of estimates Scope baseline Project schedule Resource calendars Contracts
Organizational process assets