Yolanda is the project manager for her organization. She is creating a performance report for her
sponsor. Typically, the performance report includes all of the following factors except for which
one?

PrepAway - Latest Free Exam Questions & Answers

A.
Current status of risk and issues

B.
Quality control activities

C.
Analysis of past performance

D.
Work to be completed next

Explanation:
Quality control activities are not included in the performance report, but are documented in the
quality management plan. A performance report is made by the project team detailing activities,
milestones, problems, accomplishments, and identified issues. Performance reports are used to
report some key information as follows: Current status Scheduled activities Significant
accomplishment for the period Forecasts Issues
Answer option C is incorrect. Analysis of past performance can be included in the performance
report to make the report more elaborate.
Answer option A is incorrect. Current status of risk and issues can be included in the performance
report.
Answer option D is incorrect. Work to be completed next can be included in the performance
report.