You are the project manager of the SWC project. You have created the stakeholder register. In the
stakeholder register of your project, you will have all of the following information except for which
one?

PrepAway - Latest Free Exam Questions & Answers

A.
Stakeholder classification

B.
Project management team’s classification

C.
Assessment information

D.
Identification information

Explanation:
The stakeholder register does not contain the project management team’s classification
information. The stakeholder register is a project management document that contains a list of the
stakeholders associated with the project. It assesses how they are involved in the project and
identifies what role they play in the organization. The information in this document can be very
perceptive and is meant for limited exchange only. It also contains relevant information about the
stakeholders, such as their requirements, expectations, and influence on the project.
Answer options D, C, and A are incorrect. These are the parts of the stakeholder register.