You are the project manager for your organization. You are working on creating the activity list so
that you can create the project schedule. This current project is similar to a project you have
completed for your company. You and the project team decide to use the previous project as a
template for your current project. A template can help you and the project team do all of the
following except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Identify typical schedule milestones.

B.
Create parametric estimates for repetitive activities.

C.
Save time creating activity duration estimates.

D.
Import activity attributes.

Explanation:
Parametric estimates are created for repetitive tasks, such as four hours per unit installed; 1,000
units to install would equate to 4,000 hours. A template does not address this type of time
estimating directly. A template for time estimating is an analogous estimate type. A template for
any project is an activity list or a part of the activity list from a previous project. The template
contains the activity attributes information and other vivid information that are helpful to define
activities. It is also used to classify schedule milestones.
Answer option D is incorrect. Templates can include activity attribute information.
Answer option A is incorrect. Templates do indicate milestones.
Answer option C is incorrect. Templates can save time for the project manager and the project
team.