You are working as a project manager for BlueWell Inc. Which of the following tools and
techniques of the Define Activity process will help you in identifying the typical schedule
milestones?

A.
Expert Judgment
B.
Decomposition
C.
Rolling Wave Planning
D.
Templates
Explanation:
Templates are used to identify the typical schedule milestones in the Define Activity process. The
tools and techniques used in defining the activity process are as follows: Decomposition: It is used
to further divide the project work package into a more smaller and convenient form called
activities. Rolling Wave Planning: It is a form of progressive elaboration planning where the work
to be accomplished in the near term is planned in detail and future work is planned at a higher
level of WBS. Templates: It is an activity list or a part of the activity list taken from the previous
project and used in a new project. Expert Judgement: The skilled members in a project team or
other experts who develop project scope statements can help provide knowledge in defining
activities.