Which of the following processes fall under the Project Integration Management knowledge area?
Each correct answer represents a complete solution. Choose all that apply.

A.
Quality Assurance
B.
Project Plan Development
C.
Integrated Change Control
D.
Project Plan Execution
Explanation:
Project Integration Management is one of the nine Project Management Knowledge areas. It
comprises the following processes:
Develop Project Charter
Develop Preliminary Project Scope Statement
Develop Project Management PlanDirect and Manage Project Execution
Monitor and Control Project Work
Integrated Change Control
Close Project
These processes occur throughout the project and are repeated quite often during the working of
the project. They ensure that the various elements of the project are properly coordinated. What
are the Project Management Knowledge Areas? The Project Management Knowledge Areas are
groupings that bring together processes that have things in common. For example, Resource
Planning, Cost Estimating, Cost Budgeting, etc., are part of the Project Cost Management
knowledge group. These processes may or may not be part of different or same process groups.
Guide to the PMBOK identifies forty- two processes that are arranged in nine knowledge areas.
The knowledge areas are as follows:
Project Integration Management
Project Scope Management
Project Time Management
Project Cost Management
Project Quality Management
Project Human Resource Management
Project Communications Management
Project Risk Management
Project Procurement Management
Answer option A is incorrect. Quality Assurance is a part of the Project Quality Management
knowledge area.