Which of the following is the input to monitor and control project work?

You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress
to meet the performance objectives defined in the project management plan. Mark, a trainee, has
a doubt related to the inputs of monitor and control project work. Which of the following is the input
to monitor and control project work?

PrepAway - Latest Free Exam Questions & Answers

A.
Project document updates

B.
Expert judgment

C.
Performance report

D.
Project management plan updates

Explanation:
Performance report is an input of monitor and control project work. Reports are prepared by the
project team detailing activities, milestones, and problems. A performance report is made by the
project team detailing activities, milestones, problems, accomplishments, and identified issues.
Performance reports are used to report some key information as follows: Current status Scheduled
activities Significant accomplishment for the period Forecasts Issues
Answer option B is incorrect. It is the tool and technique used for monitoring and controlling project
work.
Answer options A and D are incorrect. These are the outputs to monitor and control project work.