Which of the following is the best response for Mary’s query?

You are the project manager for GGY Project. You are working with your project team to record
the actual durations for the activities they have completed in the project schedule. Mary, one of
your project team members, wants to know why you need to know how long it actually took the
project team to complete their assignments as long as the project work is completed. Which of the
following is the best response for Mary’s query?

PrepAway - Latest Free Exam Questions & Answers

A.
Actual durations need to be recorded to track process improvement.

B.
Actual durations need to be recorded to create the schedule baseline.

C.
Actual durations need to be recorded to measure the actual progress of the project.

D.
Actual durations need to be recorded to perform quality control on the project management
processes.

Explanation:
The best answer is to track actual durations to measure the actual progress of the project. Actual
duration is the time, in the calendar units, between the actual start date of the schedule activity
and either the data date of the project schedule if the schedule activity is in development or the
actual finish date if the schedule activity is complete.
Answer option B is incorrect. The schedule baseline is not created based on actual durations.
Answer option A is incorrect. Process improvement is part of the quality management knowledge
area, but it is not a reason to track actual durations.
Answer option D is incorrect. Quality control is the inspection of the project deliverables. It is not
concerned with the actual durations of project work. The improvement of the project processes is
defined in the Process Improvement Plan.