You are the project manager for your company. You are currently working with your project team
to begin sequencing the activity list. You will need organizational process assets and four other
documents as inputs to this process. Which of the following is NOT one of the four documents you
will need for activity sequencing?

A.
Project scope statement
B.
Milestone list
C.
Project schedule network diagrams
D.
Activity list
Explanation:
The project schedule network diagram is an output of the sequence activity process, not an input.
This process uses five inputs: the activity list, the activity attributes, milestone list, the project
scope statement, and the organizational process assets. The project schedule network diagram is
an output of the sequence activity process. It represents a schematic display of the project’sschedule activities and the logical relationship among them. This diagram can be produced
manually or by using the project management software. It consists of complete project details, or
one or more summary activities.
Answer options D, B and A are incorrect. These are inputs to the process.